Whole-home remodels.
A full interior remodel that respects the house you bought. We take walls down to the studs only where the plan needs it and keep every original detail that still works.
Book a site walk
At a glance
What to expect.
- Duration
- 20–34 weeks on siteMeasured from the first day on site, after permits.
- Crew
- One superintendent, four to eight trades in sequence
- Permit path
- Building permit with Title 24 forms; historic review in Rose Garden and Naglee Park
- Warranty
- Ask about workmanship and product coverage. The applicable terms and conditions belong in your written proposal.
Included
What's in the scope.
- Selective demolition with a written keep list
- Structural changes stamped by our engineer
- New electrical, plumbing and HVAC runs wherever walls open
- Finish carpentry, paint and a line-by-line punch-list walk
- Warranty terms set out in your written proposal
Sequence
How the weeks go.
- Survey the house Two weeks. Measured drawings, a keep list, a demolition map.
- Permit Six to ten weeks.
- Demolition and structure Weeks one to five.
- Rough trades Weeks six to twelve.
- Finish Weeks thirteen to twenty-eight.
- Punch list and handover The final two weeks.
Related: Willow Glen, a 1926 craftsman lifted and rebuilt in 32 weeks