A detached backyard home for family, rent or an office. San Jose's ADU fast track means plan check in about thirty business days, and our crews build the same three plans often enough to hold the schedule.
Book a site walk
At a glance
What to expect.
- Duration
- 16–20 weeks on siteMeasured from the first day on site, after permits.
- Crew
- Three to five on site, utilities trenched in week two
- Permit path
- San Jose ADU fast track, about 30 business days, no public hearing
- Warranty
- Ask about workmanship and product coverage. The applicable terms and conditions belong in your written proposal.
Included
What's in the scope.
- Site plan, soils letter and a structural set for a 400–1,000 sq ft unit
- Utility trenching with separate sub-metering
- Full kitchen, bath, laundry and mini-split heat pump
- Fire-rated walls where the setback is under five feet
- Final inspection and certificate of occupancy
Sequence
How the weeks go.
- Choose a plan One week. Three pre-engineered plans, or your own.
- Permit About six weeks.
- Foundation and utilities Weeks one to three.
- Frame and dry in Weeks four to seven.
- Trades and finish Weeks eight to sixteen.
- Keys Week sixteen to twenty.